Cone Zones - Road and Path Closures

conezones.gif

Whether driving, walking or bicycling, caution is strongly encouraged throughout all work zones.

All of the dates and times listed in this report are weather-dependent.

Subscribe to E-News - select the "Public Works" mailing list to receive Cone Zones updates every Friday. You can also search for project-specific
e-mail lists for more targeted traffic updates.

View a map of city Cone Zones

For information on transportation options around Boulder, visit the GO Boulder Web site.

Use GOBikeBoulder.net to find detailed bike routes around Boulder.

 


followboulder.gif


Cone Zones in real time? Yeah!
Get the most up-to-date road and multi-use path closures by following Boulder Cone Zone Man on Twitter.

 

 

Cone Zones for the week of Feb. 8, 2010

City Projects

Non-City projects requiring travel restrictions


2009 Sanitary Sewer Rehabilitation Project

From 8 a.m. to 5 p.m. motorists can expect intermittent daytime lane closures and traffic delays where (work exists on the roadway or where equipment is staged); parking restrictions may also be in affect where marked.  Sewer rehabilitation will occur at the following locations and dates:

Monday, Feb 8

  • On Arapahoe from 38th east to the creek

Tuesday, Feb. 9

  • In the easement north of Benthaven Place, west of Lehigh Street

Wednesday, Feb 10

  • In the easement between Colorado Avenue and Bella Vista Lane
  • In the easement between Grandview Avenue and Marine Street, west of 9th Street

Thursday, Feb. 11

  • In the easement east of Knollwood Drive
  • In the easement between 21st and 22nd streets, north of Columbine

Friday, Feb. 12

  • In the easement between Alpine Avenue and North Street, east of 10th Street

Information: John Campagnola, City of Boulder Utilities Division, 33-441-3266

Top

Multi-use path concrete replacement work

Multi-use path concrete panel replacement work will be taking place in the following locations:

  • The Goose Creek mulit-use path, east of 28th Street at its connection to Bluff Street.
    • This work will require intermittent path closures;signed detours will be provided
  • Wonderland Creek multi-use path east of 28th Street between Kalmia Avenue and Palo Parkway.
    • This work will require that the path be closed; signed detours will be provided.

This work is expected to last approximately two weeks and will be rescheduled if weather is not favorable.

Information: Doug Rink, City of Boulder Transportation Division, 303-829-6308

30th Street Transportation Improvements Project

  • Both directions of 30th Street, in and around its intersection with Pearl Street, will have intermittent lane closures;
  • Additionally, the outside northbound lane of 30th Street, just south and north of Pearl Street will be closed 24 hours a day.  The bicycle lane on 30th Street, just north of Pearl Street, will also be closed and bicyclists are asked to merge with vehicular traffic.
  • This work is necessary while Xcel contracted crews utility undergrounding work in preparation for the 30th Street Transportation Improvements Project
  • Information: Kristopher Farruggia, NPL, 303-356-3476

Top

Valmont Road lane closures just west 28th (Utilities work)

  • Traffic will be shifted to the south side of Valmont between 26th and 28th Streets with one lane in each direction.

  • These closures are necessary to complete utility relocation work related to the Elmer's Twomile Creek Project.

  • Information:Annie Noble, City of Boulder Utilities Division, 303-441-3242

Top

Broadway (Pine to Iris) Reconstruction Project

For Broadway-specific traffic updates, sign up for the 'Public Works Broadway News' e-mail list. Choose this mailing list from the drop-down list and follow the on-screen prompts.

Work tomorrow, Saturday, Feb. 6
From 7 a.m. to 5 p.m. on Saturday, Feb. 6,  Broadway between Cedar and Elder avenues and  Evergreen Avenue and Grape Street will be reduced to one lane of alternating, flagged traffic to complete utility work.

Broadway is reduced to one lane in each direction from Balsam to Hawthorn avenues Avenue 24 hours a day.  Left turns from northbound Broadway to Hawthorn Avenue and from southbound Broadway at the North Boulder Recreation Center will be maintained.  Other left turns from Broadway in this section will be prohibited where marked.  Parking restrictions on the side streets will be in effect where marked. Pedestrian detours will also be in place.

  • Cedar, Evergreen and Forest avenues west of Broadway are closed 24 hours a day
  • From 8:30 a.m. to 4 p.m., Broadway between Hawthorn to Juniper avenues will be reduced to one lane of traffic in each direction.  One of the left turn lanes from westbound Iris to southbound Broadway also will be closed.
  • Information: Noreen Walsh, City of Boulder Transportation Division, 303-441-3266. Broadway (Pine-Iris) Reconstruction Project

Top


Non-City Projects

Note: The projects listed below are private developments and not city-sponsored. The information is provided as a service to the community. Contact information is provided when available. This list is not inclusive, and the accuracy of the information cannot be guaranteed.

63rd Street and Butte Mill Road closures due to street reconstruction

  • 63rd Street and Butte Mill Road will be closed between the Stazio Drive access roads for road reconstruction and utility installation until mid April 2010;
  • Traffic will be detoured to Stazio Drive; and
  • Mulit-use paths will not be affected.
  • Information: Stacy Maupin, DCB Construction, 720-281-484

Top

http://www.bouldercolorado.gov/index.php?option=com_content&view=article&id=10481&Itemid=3417

Clicking any flag icon above calls Google translation service to translate the page to the language you have chosen. Graphics containing text, PDF files, and special applications on this page cannot be translated. As with any computer translation, conversion is not context-sensitive and may not convert text into its intended meaning. The city of Boulder does not guarantee the accuracy of translated text. If the information you are seeking is not clear please return to the main page for the specific city department and contact them directly. Please note that some applications and/or services may not work as expected when translated.

Plugins needed for this Web site: [ Adobe Reader ] [ Flash Player ] [ Quicktime ] [ Real Player ]