Capital Investment Strategy
Round 1
Round 1 of the Capital Investment Strategy took place in 2011. A community stakeholder committee was appointed by the city manager to make a recommendation to City Council on a bond package for the 2011 ballot. The Round 1 bond package:
- does not raise taxes; and
- funds a balance of significant deficiencies to address maintenance and renovation of existing facilities as well as high priority facility enhancements.
The committee sent a recommendation to City Council to consider at its July 19, Aug. 2, and Aug. 16, 2011 meetings. The council unanimously approved the submitting to proposed bond package for the 2011 ballot on August 16. The August 16 memo to council includes the approved ordinance language.
Projects Recommended for 2011 Bond Funding
|
1
|
Replace substandard bridges, structures, signs and systems
|
$4,500,000
|
|
2
|
Arterial road reconstruction
|
$5,000,000
|
|
3
|
Replace Financial and Human Resources Software
|
$2,803,000
|
|
4
|
Facility Electrical, Plumbing, HVAC and Elevator Replacements
|
$925,000
|
|
5
|
Boulder Reservoir Infrastructure Improvements
|
$3,000,000
|
|
6
|
Police Equipment
|
$328,000
|
|
7
|
Road Pavement Repair
|
$5,000,000
|
|
8
|
Road Reconstruction
|
$2,500,000
|
|
9
|
Existing Park or Recreation Facility Renovations
|
$3,700,000
|
|
10
|
Facility Parking Lot Repair
|
$500,000
|
|
11
|
Major Business Software Replacement
|
$1,602,602
|
|
12
|
Transportation Boulder Junction Improvements
|
$5,060,000
|
|
13
|
New Wildland Fire Facilities
|
$1,150,000
|
|
14
|
Transportation Transit System Enhancements
|
$600,000
|
|
15
|
Transportation New Multi Use Path connections
|
$2,000,000
|
|
16
|
Transportation Pedestrian Enhancements
|
$850,000
|
|
17
|
Police Equipment Upgrades/ Replacement
|
$660,000
|
|
18
|
Transportation Intersection Improvements
|
$500,000
|
|
19
|
Facility Outdoor Lighting
|
$50,000
|
|
20
|
Transportation Bike System Enhancements
|
$300,000
|
|
21
|
Columbia Cemetery Upgrades/ Enhancements
|
$550,000
|
|
22
|
Facility ADA Compliance
|
$500,000
|
|
23
|
Neighborhood/ Community Park Shelter Replacements/ Improvements
|
$1,000,000
|
|
24
|
Library Facility Upgrades/ Enhancements (Children and Teen area)
|
$2,450,000
|
|
25
|
SBRC Floor Replacement
|
$100,000
|
|
26
|
Downtown Commercial District Improvements
|
$2,500,000
|
|
Recommended TOTAL
|
$48,128,602
|
Round 1 Capital Investment Strategy Committee
On May 2, 2011, City Manager Jane Brautigam appointed a 16-member Capital Investment Strategy committee to advise staff and City Council on the Capital Investment Strategy project.
For the stakeholder group's role in the project, see Operating Agreements . The committee completed the first round of its work (recommended 2011 bonding package) on July 11. The following individuals were members of the Capital Investment Strategy stakeholder group for Round 1:
Round 1 Committee
- Leslie Brown
- Natalie (Tally) Costa
- Steve Fenberg
- Nino Gallo
- Cynthia Husek
- Dan King
- Michael Kruteck
- Kristin Macdonald
- Victoria Marschner
- Miriam McGilvary
- Michael Minard
- Bill Shrum
- Max Taffet
- Leonard Thomas
- Bob Yates
- Jessica Yates
Capital Investment Strategy Committee Meeting Materials from Round 1
Past Meetings
Monday, July 11, 2011 Capital Investment Stakeholder Committee Meeting 6 - 8:30 p.m. Municipal Building Lobby, 1777 Broadway
Meeting Agenda
Meeting Materials
Monday, June 27, 2011 Capital Investment Stakeholder Committee Meeting 6 – 8:30 p.m. Municipal Building Lobby, 1777 Broadway
Meeting Agenda
Monday, June 13, 2011 Capital Investment Stakeholder Committee Meeting 6 – 8:30 p.m. Municipal Building Lobby, 1777 Broadway
Meeting Agenda
Meeting Materials
Monday, May 16, 2011 Capital Investment Stakeholder Committee Meeting 6 – 8:30 p.m. East Boulder Community Center, Eldorado Room
Meeting Agenda and Meeting Notes
Meeting Materials
Boulder Capital Investment Stakeholder Group Operating Agreements(First Draft for Stakeholder Group Discussion May 16, 2011)