Park Construction Plans and Updates

park-update.jpg

Choose a park or facility


Construction of a new neighborhood park at Dakota Blvd. and 5th St.

Impacts: Park site access restrictions during construction

Dates: Fall 2008 - December 2009

The Parks and Recreation Department is building a new neighborhood park at Dakota Blvd. & 5th St. Creation of a park in the Dakota Ridge area is a goal of the City of Boulder Parks and Recreation's current Master Plan, adopted in December 2006.

UPDATE

Construction work on Dakota Ridge park that was suspended in late May resumed on July 16, 2009.

Work was suspended after an engineering inspection of the park's concrete improvements identified contract compliance issues. The project contractor has agreed to remove, recycle and re-pour all walkways indicated in the inspection report at no additional cost to the city.

We anticipate that the construction will be completed in early November. When construction is finished, the park will be closed for an additional 30 days for lawn and plant material establishment.

The park opening celebration is scheduled for 1 to 4 p.m., Sunday, Dec. 6. More details will be posted when they are available.

For additional information, please contact the project manager, Mike Lamb at 303-413-7225.

Project Improvements:
• Shade shelters
• Quiet areas with benches
• Trees, shrubs, native grass areas and open turf play areas
• Concrete walks - loop path
• Playground area with swings
• Climbing structures
• Small scooter course
• Small climbing boulder

All park construction and restoration project dates are subject to change due to weather conditions, contractor schedules and material delivery. Therefore, dates are tentative. Updates and progress reports will be posted on this Web site as available.

This project was made possible by funds from Boulder property and sales tax revenue supporting Parks and Recreation. Thank you for your support and cooperation.

Dakota Ridge planning update


Tennis courts resurfacing

Impacts: Temporary access restrictions (work will take three to five days once started.)

List of tennis courts managed by the City of Boulder's Parks and Recreation Department

Please note that not all courts are available at all times for drop-in play, as courts may be reserved in advance by individuals and groups (for a fee).There will be temporary access restrictions to playground features.

Tentative dates (dependent on weather and contractor scheduling):
Updated Sept. 28, 2009

  • Columbine tennis courts - Done!
  • Tom Watson Park - Done!
  • Arapahoe Ridge Park - Done!
  • Manhattan Middle School - Done!
  • Centennial Middle School - Scheduled to begin Oct. 10, 2009
  • East Boulder Community Center - spring 2010

Project Details

  • Court surface restoration
  • New paint

Please Note: All park construction and restoration project dates are subject to change due to weather conditions, contractor schedules and material delivery. Therefore, dates are tentative. Updates and progress reports will be posted on this Web site as available.

This project was made possible by funds from Boulder property and sales tax revenue supporting Parks and Recreation. Thank you for your support and cooperation.

For more information, call John Cogdill at 303-441-3409
City of Boulder's Parks and Recreation Department


Melody Park playground renovations

Impacts: Temporary access restrictions to playground

Dates: Oct. 9-Nov. 30 (dependent on weather and contractor availability)

Project Improvements

  • New playground equipment
  • New picnic shelter
  • Access improvements
  • New trees

Please Note: All park construction and restoration project dates are subject to change due to weather conditions, contractor schedules and material delivery. Therefore, dates are tentative. Updates and progress reports will be posted on this Web site as available.

For more information, call Mike Lamb at 303-413-7225

City of Boulder’s Parks and Recreation Department


Park East Re-Build

Impacts: Temporary access restrictions

Dates: Early June – Spring 2010 (dependent on weather and equipment arrival)

Project Details:

  • New playground and ball court installation
  • Re-build and refurbish irrigation/landscape

Please Note: All park construction and restoration project dates are subject to change due to weather conditions, contractor schedules and material delivery. Therefore, dates are tentative. Updates and progress reports will be posted on this Web site as available.

This project was made possible by Boulder property and sales tax revenue supporting Parks and Recreation. Thank you for your support and cooperation.

For more information, call Mike Lamb at 303-413-7225

City of Boulder’s Parks and Recreation Department


Broadway (Pine-Iris) Reconstruction Project staging area at North Boulder Park

Impacts: Potential noise from equipment movement; access restrictions to 100'x100' area of park west of 9th Street at Balsam Avenue; temporary damage to staging area turf (with complete restoration at completion of project).

Dates: March 2009 - Summer 2010 (depending upon project needs/completion)

The Broadway Reconstruction Project will reconstruct Broadway from Pine Street to Iris Avenue into concrete pavement, upgrade the private and public utilities and complete some sidewalk, transit stop and streetscape enhancements.

Use Details:

  • The staging area at North Boulder Park will provide storage of construction equipment and materials for this major local, state, and federally-funded transportation improvement project.
  • All other areas of North Boulder Park will remain open for customary park activities, special events and Nordic skiing (conditions permitting), unless otherwise posted.
  • The city's contractor evaluated other potential private and public properties for this critical need, however no other sites were deemed viable given site requirements and duration of project.
  • Park staff will work closely with construction contractor to minimize impacts to park users - as well as ensuring complete park restoration upon conclusion of project.

pdf Staging Area Map 450.52 Kb

Please Note: All construction dates are subject to change due to weather conditions and other variables beyond contractor control. Therefore, dates are tentative.

Updates and progress reports on the Broadway (Pine-Iris) Reconstruction Project

For more information on the construction project, please call Noreen Walsh, Transportation Department at 303-441-3266.

For park-related questions or information, please contact Lisa Green at 303-441-3407.

North Boulder Park amenities and location


East Boulder Community ParkPark EastValmont City Park

Mesa MemorialBurke ParkCompleted ProjectsParks & Recreation news

 

Clicking any flag icon above calls Google translation service to translate the page to the language you have chosen. Graphics containing text, PDF files, and special applications on this page cannot be translated. As with any computer translation, conversion is not context-sensitive and may not convert text into its intended meaning. The city of Boulder does not guarantee the accuracy of translated text. If the information you are seeking is not clear please return to the main page for the specific city department and contact them directly. Please note that some applications and/or services may not work as expected when translated.

Plugins needed for this Web site: [ Adobe Reader ] [ Flash Player ] [ Quicktime ] [ Real Player ]