|
What's Happening NowConstruction will begin in late May 2013 and is anticipated to be completed in fall 2014. For the latest construction traffic information, visit www.boulderconezones.net and follow @boulderconezone on Twitter. If you were unable to attend the previous meetings, but have questions or comments about the Arapahoe Avenue Reconstruction Project, please complete ConstructionConstruction will begin in late May 2013 and is anticipated to be completed in fall 2014. There will be traffic and other construction impacts throughout the entire 15-to-18-month construction period. There are three phases to the construction, each with distinct traffic impacts. The most impactful work, in terms of traffic, will take place during the summers of 2013 and 2014 to take advantage of a general reduction in travelers during summer and less school and university activity. • Phase 1: June through mid-August 2013 –Stormwater and other utility relocation work. Arapahoe Avenue Traffic Detour Map • Phase 2: Mid-August 2013 to May 2014 –Construction of curbs, gutters, driveways, and sidewalks, and irrigation relocation. • Phase 3: Late May 2014 to mid-August 2014 – Concrete paving. In September and October 2014, there will be finish work and landscaping that will have include daytime single-lane closures in both directions on Arapahoe Avenue. Project OverviewProject improvements include: • Reconstruction of Arapahoe Avenue into concrete from Folsom to 17th streets and possibly to 15th Street (as funding allows); Funding Existing ConditionsThe slideshow below shows the existing conditions of Arapahoe Avenue, between Folsom and 17th streets.
MeetingsPublic Open-House Meeting - Feb. 25, 2013 Meeting Graphics and Information
Past meeting CommentIf you have questions or comments about the Arapahoe Avenue Reconstruction Project, please complete the form below.
ContactFor the latest information on construction traffic impacts associated with the project, visit www.boulderconezones.net. For more information, please call Noreen Walsh at 303-441-3266 or email This e-mail address is being protected from spambots. You need JavaScript enabled to view it . Last Updated on Friday, 24 May 2013 17:42 |



Project Background and Scope